We're looking at installing sloped floors in our brewing area and cellar area. We're working with an architect who is cost estimating it out. The sloped floors are coming in way more than we expected - ~$30,000 just for 1600 ft of concrete work. The floor coating is another $9000 and the trench drain is probably another $7-8k. The floors are being installed in an area that has brand new, reinforced concrete. They're planning to dig up the existing floor and then re-lay the entire area.
Does anyone have experience in having similar work done? What kind of price did you pay per square foot? Has anyone sloped the floors by floating concrete on top of an existing floor? Is that a cheaper way to go? Any advice?
Does anyone have experience in having similar work done? What kind of price did you pay per square foot? Has anyone sloped the floors by floating concrete on top of an existing floor? Is that a cheaper way to go? Any advice?
Comment