I need to expand my little brewery.
Currently 1BB mash tun, 1BB kettle and 2 x 1BB fermenters.
To meet demand, I was thinking of adding 2 x 5BB fermenters and 2 5BB Bright tanks and a 3BB HLT.
I am expecting to brew 3 days per week (M,W,F). Monday x 2 times to fill my 1BB fermenters, Wed x 4 times to fill 1 5BB fermenter and Fri x 4 times to fill the 2nd 5BB fermenter. Yep, I can do 2-4 times per day(have the staff) but if I get tiered I can cut short and do remainder next day.
I plan to primary for 7 days transfer to brights and 7 days and keg.
Any comments or advice would be welcome.
Currently 1BB mash tun, 1BB kettle and 2 x 1BB fermenters.
To meet demand, I was thinking of adding 2 x 5BB fermenters and 2 5BB Bright tanks and a 3BB HLT.
I am expecting to brew 3 days per week (M,W,F). Monday x 2 times to fill my 1BB fermenters, Wed x 4 times to fill 1 5BB fermenter and Fri x 4 times to fill the 2nd 5BB fermenter. Yep, I can do 2-4 times per day(have the staff) but if I get tiered I can cut short and do remainder next day.
I plan to primary for 7 days transfer to brights and 7 days and keg.
Any comments or advice would be welcome.