I am looking for a crew to install 63mm GF CoolFit on nine 20 bbl fermenters, two 20 bbl Brites, one 10 bbl Brite, and a heat exchange. The brewery is roughly 2,000 square feet. I am in a remote location in the Northwest panhandle of Florida. The GF Coolfit seems easy enough to install, but with very little plumbing experience we are more concerned with downtime, loss of income, and decreased production. I have only received one bid, which was more than the price of the materials(which is not cheap). Is the GF Coolfit as easy to install as it seems? Does anyone have any comparison/time frames it took to complete their GF Coolfit project? Bid quotes for installation? We are most likely going to do it ourselves now, but I am trying to go in as prepared as possible.